Class I Monofil, Cell 19 |
Miami Dade County Solid Waste Division |
Miami, Florida |
8 Acre Cell |
$2,900,000 |
July 2004 |
George & Associates Contractors, Inc. was contracted as the prime contractor to construct an 8-acre Class I Ash Monofill (Cell 19) at the Miami Dade County Solid Waste facility. George & Associates Contractors, Inc. is proud to have completed this project under budget and on schedule. Our responsibilities included all aspects of construction including:
- Mobilization
- Surveying
- Clearing and grubbing
- Cut and filled within cell embankment
- Excavated of 480,000 tons of materials, cut and stockpiled into Cell 20
- Finished grading and prepared sub-grade over 8-acre Cell
- Deployed GCL secondary liner, 60mm HDPE liner, planer Geo composite, bi-planer geo net, tri-planer geo net
- Installed two penetration boxes
- Installed primary leachate collection and removal system
- Installed leak detection and collection system and manhole
- Constructed anchor trench
- Exposed Cell 18 geo synthetics and tied into Cell 19
- Constructed road surface subgrade and base road around Cell 19
- Sodded around the new Cell 19
- Deployed 24" thick protective layer of sand
|
|
|
|
|
|
|